Audits Comptroller & Auditor General

CAG finds 100% vacancy of teachers and social workers in Himachal Pradesh prisons

This audit examined the compliance of the Government of Himachal Pradesh's Departments of Prisons and Correctional Services, Rural Development (MGNREGS), Animal Husbandry, and Public Works Department for the period ended March 2024.

Who it concerns: Government of Himachal Pradesh: Department of Prisons and Correctional Services, Department of Rural Development, Department of Animal Husbandry, and Public Works Department.

What the auditor found

  • Prisons: Only 36% of required guarding staff were present; teachers and social workers were 100% vacant; 40% of medical referrals failed due to escort shortages; ₹6.56 lakh owed to prisoners for misuse of their property accounts.
  • MGNREGS: 36.46% of Job Cards issued with delays (median 249 days); ₹77.47 crore in wage payments delayed; ₹15.75 crore spent on unauthorized 'Panchavati Yojna' works; ₹4.41 crore spent on inadmissible works; ₹8.67 crore procured via varied quotations instead of centralized systems.
  • Animal Husbandry: ₹68.86 crore unspent from a ₹1,562.78 crore budget; veterinary equipment lying idle due to lack of operators; delay or non-commencement of sanctioned infrastructure works.
  • Public Works: Inordinate delay of eight years in executing the Combermere Nallah bridge project due to non-compliance with procedures.
  • Recommendations: Adopt Model Prison Manual provisions, address staff shortages, ensure prescribed monitoring for MGNREGS job cards and works, and utilize tele-consultation for prison healthcare.

Also in the document

  • CAG found that in Himachal Pradesh prisons, teachers and social workers were 100% vacant, and 40% of inmates referred for hospital care could not be sent due to police escort shortages.
  • CAG reported that ₹15.75 crore was spent on 'Panchavati Yojna' works under MGNREGS without the required approval from the Government of India.
  • CAG noted that 36.46% of MGNREGS Job Cards were issued with delays, with a median delay of 249 days, and 88.72% of older cards were pending renewal or update.
  • CAG observed that the Combermere Nallah bridge project suffered an eight-year delay due to non-compliance with established works' procedures.

How this was written

An AI model running on our own computer read the government document and wrote this summary. No person has checked it.

✓ Figures checked. Every number in this summary was found in the document by an automated check.

That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.

How we work · Report an error in this story

The original document

Comptroller & Auditor General of India (CAG) — audit reports

Audit report · Ref. Report No. 3 of 2026 · 2026

Audit report 2026 · 4.4 MB Open the document On cag.gov.in ↗
Read it here

Discussion

Discuss the documents, not people. No doxxing of private individuals. Do not state allegations of crime or wrongdoing as fact — ask questions instead. Be civil. Posts that break these rules may be removed by moderators.

Sign in with Google to post

No one has discussed this document yet.