PM-KUSUM in Odisha: 18,441 pumps sanctioned, 15,780 under installation as of June 2026
The question asked by Smt. Aparajita Sarangi sought corrective measures and revised timelines for achieving solar capacity targets under PM-KUSUM in Odisha, addressed to the Ministry of New and Renewable Energy.
Smt. Aparajita Sarangi (asked), Ministry of New and Renewable Energy (answered)
- PM KUSUM is demand-driven and implemented in all states including Odisha
- State Implementing Agencies (SIAs) are responsible for implementation
- As of 30.06.2026, Component B: 18,441 pumps sanctioned, 15,780 under installation; Component A: 70 MW sanctioned, 2 MW under installation; Component C: 5,223 pumps sanctioned, 5,223 under installation
- Revised guidelines issued on 17.01.2024 to simplify procedures
- Implementation timeline extended till 31 March 2027 for projects with PPA signed by 31.12.2025
Written from the document by AI, and checked against it. The original below is authoritative.
The original document
Parliamentary Q&A
29.07.2026
Tap “Open the PDF” above to view this document.
Document details
| Official title | PM-KUSUM in Odisha |
| Source body | Parliament of India — Questions & Answers (Lok Sabha, starred) |
| Reference number | LS Q143 (Session 8) |
| Status | closed (question) |
| Year | 29.0 |
| Closing date | — |
| Documents | 1 |