Kavach Version 4.0 commissioned on 2,633 route kilometres as of 31.0

The question asked the Ministry of Railways to provide details on the commissioning milestones, high-speed trials, and schedule of the Kavach train protection system, as well as interventions for zero-accident vision. The Ministry of Railways responded with a statement detailing safety statistics, implementation progress, and budget utilization.

Asked by: Shri Godam Nagesh and Smt. Kamaljeet Sehrawat; Answered by: Ministry of Railways (Minister Shri Ashwini Vaishnaw).

  • Kavach Version 4.0 commissioned on 2,633 Route Kilometres as of 31.07.2026.
  • Approximately 470 Route Kilometres (Vadodara-Virar, Gaya-Sarmatarn, Jn Cabin-Palwal) were commissioned on 30.01.2026.
  • Kavach trials at 160 kmph were successfully held on the Chipyana Buzurg - Tundla section with a Vande Bharat Trainset.
  • Track-side Kavach implementation work has been taken up on 21,794 Route Kilometres.
  • Funds utilized on Kavach works up to June 2026 amount to Rs. 3,875 Crores, with an allocation of Rs. 2,066 Crores for 2026-27.
  • Consequential train accidents reduced from 135 in 2014-15 to 16 in 2025-26 (an 88% decrease).
  • Safety-related expenditure increased from Rs. 39,200 Crores in 2013-14 to Rs. 1,20,389 Crores in 2026-27.

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Parliamentary Q&A 05.08.2026
Tap “Open the PDF” above to view this document.
Document details
Official titleCertified Kavach Train Protection System
Source bodyParliament of India — Questions & Answers (Lok Sabha, starred)
Reference numberLS Q241 (Session 8)
Statusclosed (question)
Year05.0
Closing date
Documents1

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.

Open discussion (0) →