CAG finds ₹6,603.39 crore extra land costs in Bangalore Metro project

This performance audit examined the planning, implementation, contract management, and operation of Phase 1 and Phase 2 (excluding 2A and 2B) of the Bangalore Metro Rail Project by Bangalore Metro Rail Corporation Limited (BMRCL). The audit covered the period from the corporation's inception up to March 2021, with financial figures updated to March 2023.

Bangalore Metro Rail Corporation Limited (BMRCL), a joint venture of the Government of India and Government of Karnataka, under the Ministry of Housing and Urban Affairs.

  • Land acquisition costs increased by ₹6,603.39 crore (₹835.81 crore for Phase 1 and ₹5,767.58 crore for Phase 2) due to improper estimation and delays.
  • Excess land compensation of ₹294.72 crore was paid because BMRCL adopted non-agriculture land rates for agriculture land or added attributes applicable only to converted land.
  • Additional interest of ₹186.86 crore was paid to landowners due to delays in issuing Final Notifications beyond the 270-day timeline prescribed by the High Power Committee.
  • Excess compensation of ₹31.35 crore was paid in Phase 2 because BMRCL applied higher percentage increases to market value than prescribed by the Government of Karnataka guidelines.
  • BMRCL did not install Platform Screen Doors (PSDs) in Phase 1 underground stations, missing out on projected annual savings of ₹6.58 crore in air conditioning and maintenance costs.
  • Rails procured had hardness values (260-330 BHN) below the standard range (340-390 BHN) in 34 of 36 locations, potentially increasing maintenance costs and reducing rail/wheel life.
  • Ridership projections used for Financial and Economic Internal Rate of Return (FIRR/EIRR) calculations were overestimated, with actual 2021 traffic (6,429-8,852) far below the 15,000 threshold required to justify Heavy Metro investment.
  • BMRCL lacked a Procurement Manual, leading to a lack of uniformity in cost estimates and guidelines for project duration, package size, and advance releases.

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Audit report 2026
Tap “Open the PDF” above to view this document.
Document details
Official titleReport of the Comptroller and Auditor General of India on Implementation of Phase 1 and Phase 2 of Bangalore Metro Rail Project by Bangalore Metro Rail Corporation Limited Union Government Ministry of Housing and Urban Affairs No. 7 of 2026 (Performance Audit - Commercial)
Source bodyComptroller & Auditor General of India (CAG) — audit reports
Reference number
StatusNone (audit_report)
Year2026
Closing date
Documents1

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.

Open discussion (0) →