CAG finds ₹6,603.39 crore extra land costs in Bangalore Metro project

This performance audit examined the planning, implementation, contract management, and operation of Phase 1 and Phase 2 (excluding 2A and 2B) of the Bangalore Metro Rail Project by Bangalore Metro Rail Corporation Limited (BMRCL).

₹6,600 croreCAG found that the total increase in land acquisition costs due to estimation errors and delays amounted to over ₹6…

The audit covered the period from the corporation's inception up to March 2021, with financial figures updated to March 2023.

Who it concerns: Bangalore Metro Rail Corporation Limited (BMRCL), a joint venture of the Government of India and Government of Karnataka, under the Ministry of Housing and Urban Affairs.

What the auditor found

  • Land acquisition costs increased by ₹6,603.39 crore (₹835.81 crore for Phase 1 and ₹5,767.58 crore for Phase 2) due to improper estimation and delays.
  • Excess land compensation of ₹294.72 crore was paid because BMRCL adopted non-agriculture land rates for agriculture land or added attributes applicable only to converted land.
  • Additional interest of ₹186.86 crore was paid to landowners due to delays in issuing Final Notifications beyond the 270-day timeline prescribed by the High Power Committee.
  • Excess compensation of ₹31.35 crore was paid in Phase 2 because BMRCL applied higher percentage increases to market value than prescribed by the Government of Karnataka guidelines.
  • BMRCL did not install Platform Screen Doors (PSDs) in Phase 1 underground stations, missing out on projected annual savings of ₹6.58 crore in air conditioning and maintenance costs.
  • Rails procured had hardness values (260-330 BHN) below the standard range (340-390 BHN) in 34 of 36 locations, potentially increasing maintenance costs and reducing rail/wheel life.
  • Ridership projections used for Financial and Economic Internal Rate of Return (FIRR/EIRR) calculations were overestimated, with actual 2021 traffic (6,429-8,852) far below the 15,000 threshold required to justify Heavy Metro investment.
  • BMRCL lacked a Procurement Manual, leading to a lack of uniformity in cost estimates and guidelines for project duration, package size, and advance releases.

Also in the document

  • CAG found that the total increase in land acquisition costs due to estimation errors and delays amounted to over ₹6,600 crore.
  • CAG noted that BMRCL continued using an older Distance to Go (DTG) signaling system instead of the more advanced Communication Based Train Control (CBTC) system, which was available at the time, forcing the use of the older system in Phase 2 extensions.
  • CAG observed that Multi-Modal Integration (MMI) was not operational at eight locations as of March 2023, despite Phase 1 being fully operational since June 2017.

How this was written

An AI model running on our own computer read the government document and wrote this summary. No person has checked it.

✓ Figures checked. Every number in this summary was found in the document by an automated check.

That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.

How we work · Report an error in this story

The original document

Comptroller & Auditor General of India (CAG) — audit reports

Audit report · 2026

Audit report 2026 · 13.3 MB Open the document On cag.gov.in ↗