Audits Comptroller & Auditor General
REC cuts state demand for grid upgrades from ₹44,821.22 crore to ₹12,412.55 crore
This performance audit examined the implementation, financial management, and monitoring of the Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY) and Pradhan Mantri Sahaj Bijli Har Ghar Yojana (SAUBHAGYA) schemes.
The audit covered projects sanctioned up to March 2020, with observations updated through December 2023.
Who it concerns: Union Government, Ministry of Power, and the 27 States and 3 Union Territories involved in the schemes.
What the auditor found
- REC restricted the System Strengthening component cost demanded by states from ₹44,821.22 crore to ₹12,412.55 crore, a reduction ranging from 14.13% to 99.05%.
- Feeder separation costs demanded by seven states (₹11,285.78 crore) were restricted to ₹3,967.20 crore, a reduction of 46.27% to 100%.
- AT&C loss targets were not fully achieved in 12 States and one UT, resulting in a lesser grant release of ₹3,631.62 crore to DISCOMs.
- Only 7,833 agricultural feeders were separated by March 2022, against 9,019 sanctioned and 16,500 approved by the CCEA.
- REC released ₹541.56 crore as first instalments to six states 13 to 360 days before the execution of required agreements.
- Early payment of ₹1,603.81 crore (60% of eligible grant) was made to six states without ensuring timely state contribution.
- Under RGGVY, REC released ₹246.28 crore in capital subsidy during 2014-15, while project works were not awarded until April 2015 to May 2017.
- Delays in award occurred in 494 projects (81.65%) out of 605, with 184 projects delayed by more than 12 months.
- Delays in completion occurred in 555 projects (91.74%) out of 605, with 263 projects delayed by more than 24 months.
- CAG recommended that the Ministry of Power ensure feasibility studies and detailed field surveys before preparing Detailed Project Reports (DPRs) to minimize variations.
- CAG recommended standardizing procedures for project award and execution to ensure timely completion.
Also in the document
- The audit found that the allocated budget for system strengthening and feeder separation was insufficient to meet the scheme's objectives, leading to significant restrictions on state demands.
- A large majority of projects (over 80% for award and over 90% for completion) experienced delays beyond the stipulated timelines.
- Funds were released in violation of guidelines, including payments made before the execution of necessary agreements or before project award.
How this was written
An AI model running on our own computer read the government document and wrote this summary. No person has checked it.
✓ Figures checked. Every number in this summary was found in the document by an automated check.
That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.
The original document
Comptroller & Auditor General of India (CAG) — audit reports
Audit report · Ref. Report No. 17 of 2025 · 2025
Discussion
No one has discussed this document yet.