CAG finds ₹255.75 crore in fake bidder contracts awarded by UPSIDA
This performance audit examined the working of the Uttar Pradesh State Industrial Development Authority (UPSIDA) for the period 2017-18 to 2021-22 (updated up to March 2024).
₹255.75 croreCAG found that UPSIDA awarded 15 contracts totaling ₹255.75 crore without verifying bidder documents, which were la…
It assessed land acquisition, infrastructure development, plot allotment, and internal financial controls.
Who it concerns: Uttar Pradesh State Industrial Development Authority (UPSIDA), Government of Uttar Pradesh
What the auditor found
- Lapses in planning: Failure to prepare Perspective, Development, or Zonal plans since constitution.
- Land acquisition targets missed in 4 out of 6 years, with shortfalls ranging from 27.60% to 100%.
- Infrastructure targets missed in all 6 years, with shortfalls ranging from 24.67% to 92.70%.
- 15 contracts worth ₹255.75 crore awarded without verifying bidder documents; later cancelled due to suspected fake documents.
- 27 contract bonds (₹1.01 crore to ₹63.41 crore) awarded without assessing bidding capacity, causing delays.
- Short recovery of Liquidated Damages (LD) of ₹13.71 crore in 16 cases.
- Failure to recover quality test fees of ₹1.63 crore from contractors in 34 works.
- Avoidable expenditure of ₹7.67 crore on maintenance of areas under municipal bodies.
- Plot allotment targets missed (27-58% achievement) and recovery targets missed (47-96% achievement).
- Allotment of plots to ineligible applicants and excess land allotment (1,992 sqm to 10,542 sqm) due to lack of evaluation criteria.
- Short recovery of ₹58.98 lakh from e-auctions due to violation of Board-approved procedures.
- Permission for start of production granted before completion/occupancy certificates in 37 cases.
- Annual accounts not prepared for UPSIDA, UPSIDC, or Ex-LIDA, preventing legislative oversight.
- Unsecured loans of ₹52.84 crore granted to two state PSUs.
- Investment of ₹57.23 crore in fixed deposits in violation of guidelines.
- TDS refunds of ₹60.33 lakh not claimed timely.
Also in the document
- CAG found that UPSIDA awarded 15 contracts totaling ₹255.75 crore without verifying bidder documents, which were later suspected to be fake and cancelled.
- CAG noted that UPSIDA incurred avoidable expenditure of ₹7.67 crore on maintaining industrial areas that fall under the jurisdiction of municipal bodies.
- CAG reported that annual accounts for UPSIDA, UPSIDC, and Ex-LIDA were not prepared, meaning they were not laid before the Legislature.
- CAG found that UPSIDA granted unsecured loans of ₹52.84 crore to two state Public Sector Undertakings.
How this was written
An AI model running on our own computer read the government document and wrote this summary. No person has checked it.
✓ Figures checked. Every number in this summary was found in the document by an automated check.
That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.
The original document
Comptroller & Auditor General of India (CAG) — audit reports
Audit report · Ref. Report No. 14 of 2025 · 2025
Read it here
Discussion
No one has discussed this document yet.