Supreme Court quashes re-tendering of road work, extends three months for completion

The case involves a challenge to the High Court's decision quashing a tender award and directing re-tendering, raised through a PIL by an unsuccessful bidder questioning the comparative assessment of bids.

Petitioner: O.P. Mehta; Respondents: Mohinder Kalta & Ors.; Bench: Justice Sheel Nagu

  • Quashed the High Court's order directing re-tendering of road work
  • Extended three months for appellant to complete work at 15.03.2024 rates
  • If work not completed within three months, re-tender at prevailing market rate
  • Directing official respondents to verify quality of work
  • Deferred to first week of December 2026 for compliance report
  • Interim order dated 07.03.2025 modified to continue subsisting

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Order 2026-09-23
Tap “Open the PDF” above to view this document.
Document details
Official titleSupreme Court Frowns Upon PIL Challenging Inter-Se Assessment Of Tender Bids
Source bodySupreme Court of India — orders & judgments
Reference number
Statusclosed (order)
Year2026
Closing date
Documents1