Bajaj Auto expands 677,751 sq. mt industrial shed on 362.64 ha non-forest land
This clearance is for the expansion of an industrial shed construction project by Bajaj Auto Limited at Plot No-A1 Waluj MIDC in Sambhajinagar (Aurangabad), Maharashtra. The project involves increasing the built-up area to approximately 677,751 square meters on non-forest land.
The project proponent is Bajaj Auto Limited (represented by Jayant Kulkarni). The clearance was granted by the State Environment Impact Assessment Authority (SEIAA), Maharashtra.
- Clearance Status: Fresh Environmental Clearance (EC) granted under Category B1.
- Land Area: 362.64 hectares of Non-Forest Land; 0 hectares of Forest Land.
- Project Cost: 23,000 lakhs (approx. 230 Crores).
- EMP Cost: 3,098 lakhs.
- Condition: Obtain IOD/IOA/Concession documents and mandatory NOCs from planning authorities.
- Condition: Increase depth of rainwater harvesting pits.
- Condition: Reduce Parijatak trees by 50-80% and plant high-sequestration trees like Peepal, Banyan, Audumbar, and Umbar.
- Condition: Implement a plan to make the project site a plastic-free zone.
- Condition: Ensure treated sewage meets National Green Tribunal standards (order dated 30.04.2019) and do not use drinking water for construction.
- Condition: Manage construction and demolition waste as per 2016 Rules.
- Condition: Provide electric vehicle charging facilities as per Maharashtra Electric Vehicle Policy, 2025.
- Condition: Achieve minimum 5% energy saving using non-conventional energy sources.
Written from the document by AI, and checked against it. The original below is authoritative.
The original document
Clearance
2026-05-23
Tap “Open the PDF” above to view this document.
Document details
| Official title | Expansion in Proposed Industrial Shed Construction Project at Plot No-A1 Waluj MIDC, gut no 365, 366, 367, 368 Waluj, Gut no 25 & 26 Naigaon Chh. Sambhajinagar, (Aurangabad) Maharashtra – 431136 by M/s. Bajaj Auto Limited. |
| Source body | PARIVESH — Environmental & Forest Clearances (MoEFCC) |
| Reference number | SIA/MH/INFRA2/579740/2026 |
| Status | closed (clearance) |
| Year | 2026 |
| Closing date | — |
| Documents | 1 |