Nat’l Highways Infra Dev Corp

NHIDCL extends bid deadline to 29/09/2025 for ₹98.05 crore Jammu-Kashmir road project

NHIDCL is inviting bids for the construction of leftover work (2-lane with paved shoulder) on a 4.037 km stretch of NH-244 in Jammu & Kashmir under an Engineering, Procurement, and Construction (EPC) contract.

Who can bid: The document states that bids are invited from 'eligible contractors' but does not specify the detailed eligibility criteria such as minimum turnover, years of experience, or required certifications in the provided text.

Key terms

  • Estimated Cost: Rs. 98.05 Crore (exclusive of GST)
  • Bid Security: Rs. 0.99 Crore
  • Completion Period: 2 years
  • Maintenance Period: 5 years
  • Tender Type: EPC Mode
  • Bid Submission Deadline: 29/09/2025 (as per Corrigendum 02)
  • Bid Opening Date: 30/09/2025 (as per Corrigendum 02)

Also in the document

  • The bid submission deadline was extended from 22/09/2025 to 29/09/2025 via Corrigendum 02.

How this was written

An AI model running on our own computer read the government document and wrote this summary. No person has checked it.

✓ Figures checked. Every number in this summary was found in the document by an automated check.

That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.

How we work · Report an error in this story

The original document

National Highways & Infrastructure Development Corporation (NHIDCL)

Tender · 7 Aug 2025

Notice 7 Aug 2025 · 0.3 MB Open the document On nhidcl.com ↗
Notice 7 Aug 2025 On nhidcl.com ↗
Notice 7 Aug 2025 On nhidcl.com ↗
Notice 7 Aug 2025 On nhidcl.com ↗
Notice 7 Aug 2025 On nhidcl.com ↗
Corrigendum 1 7 Aug 2025 · scanned image · 1.2 MB Open the document On nhidcl.com ↗
Corrigendum 2 7 Aug 2025 · 0.4 MB Open the document On nhidcl.com ↗
Read it here
Questions a citizen might ask

Observations drawn mechanically from the documents — not findings or allegations.

  • The department changed this document 2 times after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?

Discussion

Discuss the documents, not people. No doxxing of private individuals. Do not state allegations of crime or wrongdoing as fact — ask questions instead. Be civil. Posts that break these rules may be removed by moderators.

Sign in with Google to post

No one has discussed this document yet.