NHIDCL to spend ₹14.42 crore on 57 km highway upgradation in Assam
NHIDCL is inviting proposals for Project Management Consultancy (PMC) services to oversee the upgradation of National Highway 15 (NH-15) from a 2-lane with passing section to a 4-lane configuration in Assam, covering a length of 57.00 km.
The document invites proposals from 'eligible consultants' but does not specify minimum turnover, years of experience, or specific certifications in this text. Bidders must mandatorily register on the MoRTH 'INFRACON' portal, form a Team to obtain a unique Infracon Team ID, and submit the proposal online via the e-tender portal.
- Tender Type: Open (Notice Inviting Tender)
- Tentative Estimate PMC Cost: Rs. 14.42 crore (excluding GST)
- Assignment Period: 108 months (10 months + 8 months + 30 months + 60 months)
- Bid Document Fee: INR 5,900 (non-refundable, including GST)
- Bid Due Date: 04.12.2025 at 1500 Hrs
- Bid Validity: 120 days from Bid due date
Written from the document by AI, and checked against it. The original below is authoritative.
The original document
Document details
| Official title | Upgradation from 2 Lane with PS to 4 Lane configuration of NH-15 from Ch 381+000 at Gogamukh to Ch 438+000 at Kulajan Tiniali in the State of Assam |
| Source body | National Highways & Infrastructure Development Corporation (NHIDCL) |
| Reference number | — |
| Status | closed (archive) |
| Year | 2025 |
| Closing date | 04-12-2025 |
| Documents | 6 · changed 1× after publishing |
Observations & questions a citizen might ask
Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.
- The department changed this document 1 time after first publishing it.
- What prompted each amendment, and was the closing date extended to give bidders time to respond?
- Do the eligibility and scope requirements match the stated purpose and estimated value?
- Were all amendments published on the portal before the deadline?