कौन ज़िम्मेदार? KaunZimmedar

NHIDCL to spend ₹19.19 crore on 12-month NH-110 maintenance contract

The National Highways and Infrastructure Development Corporation Ltd. (NHIDCL) is contracting for short-term maintenance work on National Highway 110 (Old NH-55) from 00.00km to 43.00km in Darjeeling district, West Bengal, including machinery deployment and incident management, under a percentage rate contract for FY 2025-26.

Bidders must have an average annual turnover of at least Rs. 19.19 Cr. over the last 3 years, or a single work of Rs. 6.72 Cr. (minimum 35% of estimated cost) or two similar works each of Rs. 4.80 Cr. (minimum 25% of estimated cost) over the last 5 years.

  • Estimated cost: Rs. 19.19 Cr. (inclusive of GST)
  • Security amount: Rs. 0.1919 Cr. (Nineteen Lakh Nineteen Thousand)
  • Tender type: Open (e-tendering)
  • Bid submission deadline: 27-01-2026
  • Bid validity: 120 days
  • Contract duration: 12 months (maintenance period-12 months)

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Notice 2026-01-07
Tap “Open the PDF” above to view this document.
Notice 2026-01-07
Corrigendum 1 2026-01-07 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 2 2026-01-07 scanned
Tap “Open the PDF” above to view this document.
Document details
Official titleShort Term Maintenance Contract (STMC) work from 00.00km (at Darjeeling more) to 43.00km (at Giddha Pahar) NH-110 [Old NH-55] [Including the provision for Deployment of Machineries & Incident management] in the district of Darjeeling under NHIDCL on Percentage Rate Contract Basis during the FY 2025-26 in the state of West Bengal.
Source bodyNational Highways & Infrastructure Development Corporation (NHIDCL)
Reference number
Statusclosed (archive)
Year2026
Closing date27-01-2026
Documents4 · changed 2× after publishing
Observations & questions a citizen might ask

Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.

  • The department changed this document 2 times after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?

📄 Draft an RTI to ask what the documents don't say

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.

Open discussion (0) →