कौन ज़िम्मेदार? KaunZimmedar

NHIDCL to spend ₹892 crore on 58.342 km Assam road project

NHIDCL is inviting bids for the construction of a 2-lane road with paved shoulders on the existing NH-137G in Assam (58.342 km length) under a Hybrid Annuity (DBOT) model.

The document states that the Authority seeks to select a 'private entity' as the Bidder. Specific eligibility criteria such as minimum turnover, years of experience, or required certifications are not stated in this text.

  • Estimated Project Cost: Rs. 798.93 Cr (Excl. GST)
  • Project Cost (As on date of Appraisal by SFC/PPPAC): Rs. 892.00 Cr (Excl. GST)
  • Tender Type: Hybrid Annuity Mode (DBOT)
  • Bid Submission Deadline: 26.03.2026 (up to 1100 Hrs. IST)
  • Technical Bid Opening: 27.03.2026 (at 1130 hours IST)
  • Bid Security Submission: Physically within 5-working days of the Bid Due Date

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Notice 2026-02-10
Tap “Open the PDF” above to view this document.
Notice 2026-02-10
Notice 2026-02-10
Notice 2026-02-10
Notice 2026-02-10
Notice 2026-02-10
Notice 2026-02-10
Corrigendum 1 2026-02-10 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 2 2026-02-10 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 3 2026-02-10 scanned
Tap “Open the PDF” above to view this document.
Document details
Official titleConstruction of 2-Lane with paved shoulder of Existing Intermediate Lane of NH-137G from Village near Pailapool at Design Ch. 0+00 (Ch. 20.800 of Silchar Jiribam Pkg-I, NH-37) to Village P.Songkai at Design Ch. 58+342 (Ch. 106+830 of Tamenglong- Mahur section of NH-137) near Hangrum (Length: 58.342 km) in the State of Assam under NH(O)-NE on Hybrid Annuity Mode
Source bodyNational Highways & Infrastructure Development Corporation (NHIDCL)
Reference number
Statusclosed (archive)
Year2026
Closing date30-06-2026
Documents10 · changed 3× after publishing
Observations & questions a citizen might ask

Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.

  • The department changed this document 3 times after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?