NHIDCL to spend ₹13.35 crore on 21.10 km NH-717A upgrade in West Bengal

The National Highways and Infrastructure Development Corporation Ltd. (NHIDCL) is inviting bids for the construction and upgradation of a 21.10 km section of NH-717A from Kafer to Lava in West Bengal, including geometric improvements, paved shoulders, and associated civil works, to be completed within 12 months during FY 2026-2027.

Bidders must have an average annual turnover of at least Rs. 13.35 crore over the last 3 years, or a single work of Rs. 6.68 crore (minimum 50% of estimated cost), or two similar works each of Rs. 4.67 crore (minimum 35% of estimated cost), or three similar works each of Rs. 3.34 crore (minimum 25% of estimated cost) over the last 5 years.

  • Estimated cost: Rs. 13,34,87,922/- (exclusive of GST)
  • Security amount: Rs. 26,69,000/-
  • Bid submission deadline: 06.07.2026
  • Bid validity: 120 days
  • Contract duration: 12 months

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Notice
Tap “Open the PDF” above to view this document.
Corrigendum 1 scanned
Corrigendum 2 scanned
Document details
Official titleBalance work under Risk and Cost for Construction and Upgradation of Existing Road to 2- Lane with Paved shoulders including geometric improvement of section from Kafer to Lava more km 40.00 to km 61.100 of NH-717A in the state of West Bengal during the FY 2026-2027 (Package-VA) on percentage rate basis
Source bodyNational Highways & Infrastructure Development Corporation (NHIDCL)
Reference number
Statusclosed (current)
Year2026
Closing date06-08-2026 17:00:00
Documents4 · changed 2× after publishing
Observations & questions a citizen might ask

Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.

  • The department changed this document 2 times after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?

📄 Draft an RTI to ask what the documents don't say