Development, Maintenance, Management and Operation of Greenfield High-Speed Corridor from Ma…

NHIDCL is inviting bids for the development, maintenance, management, and operation of a 54.720 km section of a greenfield high-speed corridor (Package-3) on a Hybrid Annuity basis.

The document states that the Ministry has decided to select a 'private entity' as the Bidder. Specific eligibility criteria such as minimum turnover, years of experience, or required certifications are not stated in this text.

  • Estimated Project Cost (Excluding GST): Rs 5003.67 Cr
  • Estimated Project Cost (Excluding GST): Rs 5513.50 Cr
  • Tender Type: Hybrid Annuity
  • Bid Submission Deadline: 03.08.2026 (up to 1500 Hrs. IST)
  • Technical Bid Opening: 04.08.2026 (at 1500 hours IST)
  • Bid Security Submission: Physically within 5 working days of the Bid Due Date

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Notice 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 1 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 2 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 3 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 4 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 5 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Corrigendum 6 2026-06-12 scanned
Tap “Open the PDF” above to view this document.
Document details
Official titleDevelopment, Maintenance, Management and Operation of Greenfield High-Speed Corridor from Mawlyngkhung (near Shillong) in Meghalaya to Panchgram (near Silchar) in Assam by 4-Laning with Paved Shoulders on Hybrid Annuity Basis. (Package-3: From Km 78+600 to Km 133+320, Design Length – 54.720 Km).
Source bodyNational Highways & Infrastructure Development Corporation (NHIDCL)
Reference number2026_NHIDC_912874_1
Statusclosed (archive)
Year2026
Closing date21-09-2026
Documents7 · changed 6× after publishing
Observations & questions a citizen might ask

Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.

  • The department changed this document 6 times after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?