Environmental Clearance granted for 91,561.89 sq m storage building project in Thane
This document grants Environmental Clearance (EC) for a proposed storage building project located in Village Kamatghar, Taluka Bhiwandi, District Thane, Maharashtra.
The project involves construction activities on specific land parcels and does not involve the manufacturing of products.
Who it concerns: The project proponent is M/s Bhumi Corporation Pvt Ltd (represented by Mr. Kapil Patel). The clearance was granted by the State Environment Impact Assessment Authority (SEIAA), Maharashtra.
Conditions and facts
- Clearance Status: Environmental Clearance (EC) granted under EIA Notification 2006, Category B2, Schedule No. 8(a) Building/Construction.
- Project Size: 91,561.89 square meters.
- Condition: The project proponent must obtain a Solid Waste Management (SWM) NOC.
- Condition: The project proponent must prepare and implement a plan to make the proposed project a plastic-free zone.
- Condition: The project proponent must obtain IOD/IOA/Concession Document/Plan Approval or other documents clarifying conformity with local planning rules and Supreme Court orders regarding Reserved Green (RG) area.
- Condition: The project proponent must submit an undertaking signed by the proponent, consultant, and architect certifying no violation of EIA Notification 2006.
- Condition: Specific technical requirements for underground suction tanks, including distance from drainage lines and head clearance for inspection.
- Condition: Treated sewage must meet parameters set by the National Green Tribunal order dated 30.04.2019.
- Condition: Tree plantation must be completed within the site during the construction phase.
- Condition: Compliance with Solid Waste Management Rules 2026, Environment (Construction and Demolition) Waste Management Rules 2025, and E-Waste (Management) Rules 2022.
Also in the document
- The document explicitly states that the project does not involve the manufacturing of any product or by-product.
- The clearance is subject to the condition that the planning authority shall not grant an occupation certificate unless the project proponent obtains all mandatory NOCs from competent authorities.
How this was written
An AI model running on our own computer read the government document and wrote this summary. No person has checked it.
✓ Figures checked. Every number in this summary was found in the document by an automated check.
That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.
The original document
PARIVESH — Environmental & Forest Clearances (MoEFCC)
Clearance · Ref. SIA/MH/INFRA2/584663/2026 · 14 Jul 2026
Read it here
Discussion
No one has discussed this document yet.