कौन ज़िम्मेदार? KaunZimmedar

NHIDCL sets ₹20.2 crore price for West Bengal highway work, 12-month construction

NHIDCL (Ministry of Road Transport & Highways) is contracting for slope protection, landslide mitigation, and reconstruction of a 200-meter culvert on NH-110 near Tindhariya, West Bengal, on an EPC (Engineering, Procurement, and Construction) basis.

The document invites International Competitive Bids from eligible contractors. Specific eligibility criteria such as minimum turnover, years of experience, or required certifications are not stated in the provided text, though bidders must provide statutory auditor certifications with UDIN and self-certify local content status.

  • Estimated Cost: Rs. 20,20,80,134.00 (exclusive of GST)
  • Bid Security: Rs. 20,21,000.00
  • Completion Period: 12 months construction + 60 months DLP (Defects Liability Period)
  • Tender Type: Online e-tender via Central Public Procurement Portal (CPPP)
  • Bid Submission Deadline: 14.09.2026
  • Bid Opening Date: 15.09.2026
  • Price Adjustment: Not payable to the Contractor

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Notice 2026-08-24
Tap “Open the PDF” above to view this document.
Corrigendum 1 2026-08-24 scanned
Tap “Open the PDF” above to view this document.
Document details
Official titleSlope protection and landslide mitigation and Re-construction of culvert from km 23.000 to km 23.200 (200 mtr. approx.) near Tindhariya on NH-110 on EPC mode in the State of West Bengal during FY 26-27.
Source bodyNational Highways & Infrastructure Development Corporation (NHIDCL)
Reference number2026_NHIDC_923506_1
Statusactive (current)
Year2026
Closing date25-09-2026 17:00:00
Documents2 · changed 1× after publishing
Observations & questions a citizen might ask

Factual observations drawn mechanically from the documents — not findings or allegations. Verify each against the original.

  • The department changed this document 1 time after first publishing it.
  • What prompted each amendment, and was the closing date extended to give bidders time to respond?
  • Do the eligibility and scope requirements match the stated purpose and estimated value?
  • Were all amendments published on the portal before the deadline?

📄 Draft an RTI to ask what the documents don't say

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.

Open discussion (0) →