Four-laning of NH-75: 98% complete for Package I, 94.21% for Package II
The question asked for the physical and financial progress, operational status of specific structures, monsoon-related work suspensions, and revised completion dates for the four-laning of National Highway-75 from Addahole to Bantwal. The answer was provided by the Ministry of Road Transport and Highways.
Asked by Shri Captain Brijesh Chowta; Answered by the Ministry of Road Transport and Highways (Minister Shri Nitin Jairam Gadkari).
- The project is divided into two packages: Package I (Addahole to Periya Shanthi, 15.13 km) and Package II (Periya Shanthi to Bantwal, 48.48 km).
- Physical progress is 98% for Package I and 94.21% for Package II.
- In Nellyadi, the SVUP-01 structure and 2.54 km service road are completed and open; the Flyover-01 has its Left Hand Side (LHS) open and Right Hand Side (RHS) closed; the Vertical Underpass (VUP-01) is closed.
- In Kalladka, the Flyover-01 and 5.99 km service road are completed and open for traffic.
- Work in approximately 1.3 km has been rescheduled due to a stay on the Elephant Underpass construction, compensation demands, and additional work.
- Bituminous resurfacing and safety signage were installed at affected locations to ensure traffic flow during monsoon.
- Revised completion date for Package I is 30.03.2027.
- Revised completion date for Package II is 30.04.2027.
Written from the document by AI, and checked against it. The original below is authoritative.
The original document
Parliamentary Q&A
23.07.2026
Tap “Open the PDF” above to view this document.
Document details
| Official title | Four-laning of National Highway-75 |
| Source body | Parliament of India — Questions & Answers (Lok Sabha, starred) |
| Reference number | LS Q67 (Session 8) |
| Status | closed (question) |
| Year | 23.0 |
| Closing date | — |
| Documents | 1 |