109.38 Ha ash pond land acquisition underway for Odisha power plant expansion
This document concerns the expansion of an existing coal-based thermal power plant in Jharsuguda district, Odisha, by adding two new units of 660 MW each (Stage-III).
The project aims to increase the total generation capacity from 1740 MW to 3060 MW.
Who it concerns: The project proponent is M/s. Odisha Power Generation Corporation Limited (OPGCL). The clearance is being processed by the Ministry of Environment, Forest and Climate Change (MoEF&CC), specifically the IA Division.
Conditions and facts
- Clearance Status: Fresh Environmental Clearance (EC) application under Category A of the EIA Notification 2006.
- Capacity: Addition of 2x660 MW (1320 MW) to the existing 1740 MW plant.
- Land: No additional land is required for the main plant area; the expansion uses existing available land of 60.703 Ha.
- Ash Pond: A new 109.38 Ha ash pond is proposed for Stage-III, located 7 km from the plant area; 34.78 Ha of this is earmarked for greenbelt development.
- Ash Pipeline: A 5.69 Ha right-of-way corridor is proposed for the Stage-III ash pipeline.
- Emissions: A 275m twin-flue stack is planned for the new units; FGD installation for existing Stage-II units is 90% complete and expected to be commissioned by 31.12.2026.
- Compliance: The proponent reported 6 partially complied conditions from the previous EC; 5 are now stated as complied, and 1 remains partially complied.
Also in the document
- The project site is in close proximity to sensitive receptors, including schools (e.g., DAV Public School at 1 km) and hospitals (e.g., ITPS Hospital at 1.5 km).
- The document notes that the Stage-III ash pond land (109.38 Ha) is currently under the process of acquisition by IDCO, with administrative approval accorded by the Odisha Energy Department on 29/04/2026.
How this was written
An AI model running on our own computer read the government document and wrote this summary. No person has checked it.
✓ Figures checked. Every number in this summary was found in the document by an automated check.
That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.
The original document
PARIVESH — Environmental & Forest Clearances (MoEFCC)
Clearance · Ref. IA/OR/THE/575779/2026 · 19 May 2026
Read it here
Discussion
No one has discussed this document yet.