This is an Environmental Clearance (EC) for a proposed residential building project located at Survey Nos. 69/4(P) and 69/5(P) in Kharadi, Haveli Taluka, Pune District, Maharashtra.
The project involves construction activities with a total built-up area of 37,516 square meters.
Who it concerns: The project proponent is M/s. Marvel Realtors & Developers Limited (represented by Vikas Tolani). The clearance was granted by the State Environment Impact Assessment Authority (SEIAA), Maharashtra.
Conditions and facts
- Clearance Status: Granted by SEIAA on 28/07/2026 following a meeting on 20/07/2026.
- Project Size: Total built-up area of 37,516 Sq.m.
- Condition: Proponent must obtain IOD/Plan Approval and all mandatory NOCs from the planning authority, ensuring conformity with local planning rules and Supreme Court orders on RG area.
- Condition: Proponent must submit a revised IOD in the name of M/s Marvel Realtors & Developers Pvt Ltd, as the current IOD is in the name of M/s Marvel Promoters and Developer Pvt Ltd.
- Condition: Project must be a plastic-free zone.
- Condition: Treated sewage must meet National Green Tribunal standards (order dated 30.04.2019), and drinking water must not be used for construction.
- Condition: Construction and demolition waste must be managed as per the 2016 Rules.
- Condition: Electric vehicle charging facilities must be provided as per the Maharashtra Electric Vehicle Policy, 2025.
- Condition: Minimum 5% energy saving must be achieved using non-conventional energy sources.
Also in the document
- The document notes a discrepancy in the name of the entity holding the IOD (Marvel Promoters and Developer Pvt Ltd) versus the project proponent (Marvel Realtors & Developers Pvt Ltd), requiring a revised IOD.
- The clearance explicitly states that it does not tantamount to approvals under other Acts or regulations, which the proponent must still obtain.
How this was written
An AI model running on our own computer read the government document and wrote this summary. No person has checked it.
✓ Figures checked. Every number in this summary was found in the document by an automated check.
That check compares numbers only. It cannot confirm that the wording says what the document says — so the original document is always the authority.
The original document
PARIVESH — Environmental & Forest Clearances (MoEFCC)
Clearance · Ref. SIA/MH/INFRA2/579773/2026 · 25 May 2026
Read it here
Discussion