Environmental clearance granted for Pune township project with tree replacement condition

This document grants prior Environmental Clearance for the new construction project 'Rohan Abhilasha 5', a township/area development project located in Wagholi, Haveli Taluka, Pune district, Maharashtra.

The project proponent is M/s. Rohan Builders and Developers Pvt. Ltd. (represented by Milind Lunkad), and the clearance was granted by the State Environment Impact Assessment Authority (SEIAA), Maharashtra.

  • Clearance Status: Fresh Environmental Clearance (Category B1) granted on 28/07/2026.
  • Land Area: 12.734 hectares of Non-Forest Land (0 hectares of Forest Land).
  • Project Cost: 101,000 lakhs (approx. 1,010 Crores INR).
  • Condition: Replace Saptaparni, Parijatak, and Sonchafa trees with other indigenous species in the plantation plan.
  • Condition: Implement a plan to make the project a plastic-free zone.
  • Condition: Ensure treated sewage meets National Green Tribunal standards (order dated 30.04.2019) and do not use drinking water for construction.
  • Condition: Provide electric vehicle charging facilities as per the Maharashtra Electric Vehicle Policy, 2025.
  • Condition: Achieve minimum 5% energy saving using non-conventional energy sources.

Written from the document by AI, and checked against it. The original below is authoritative.

The original document

Clearance 2026-06-12
Tap “Open the PDF” above to view this document.
Document details
Official titleNew Construction Project “Rohan Abhilasha 5” at Wagholi Haveli Pune by Rohan Builders and Developers Pvt. Ltd.
Source bodyPARIVESH — Environmental & Forest Clearances (MoEFCC)
Reference numberSIA/MH/INFRA2/568881/2026
Statusclosed (clearance)
Year2026
Closing date
Documents1

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.