Report No. 4 of 2026-Report of the Comptroller and Auditor General of India on State Finances for the year 2024-25

CAG closed 2026
Plain-language summary (AI-generated) — a quick read so you don't have to open the full PDF. May contain errors; the original document below is authoritative.

What did the audit examine?

The audit examined the implementation of the Jal Jeevan Mission (JJM) in Madhya Pradesh from 2019-20 to 2023-24, focusing on planning, execution, monitoring, and outcomes of the scheme.

Who / what it concerns

Government of Madhya Pradesh (specifically the Public Health Engineering Department and MP Jal Nigam)

What the auditor found

  • Systemic planning deficiencies including absent or delayed baseline surveys leading to inaccurate assessments and cost escalations
  • Community engagement was superficial with near-zero financial participation (community contributions)
  • Only 27% of Multi-Village Schemes and 58% of Single-Village Schemes completed as of September 2024
  • Flawed estimations causing cost escalations, avoidable expenditures, inflated tenders, and richer specifications
  • Non-issuance of physical completion certificates in SVSs with 7 of 28 inspected sites found non-functional
  • Liquidated damages not recovered from contractors
  • Only 0.38% of funds earmarked for water quality monitoring were spent, with 1.62% diverted for construction
  • Water quality testing conducted at only 58-99% (district labs), 22-48% (State Lab), and 11-19% (Jal Nigam WTP) of prescribed frequency
  • 11,94,063 private/own source tap connections incorrectly included in JJM FHTCs in the portal

Points worth noting

  • Only 60.90 lakh rural households covered by December 2024 out of a target of 1.12 crore FHTCs
  • 13.53 lakh households already had tap connections before JJM began
  • Madhya Pradesh lagged with 69% coverage vs national 80%
  • Only 18 of 33 fluoride-affected villages in Dindori District had Electrolytic Defluorination Units by December 2021
  • 11,94,063 private/own source tap connections incorrectly counted as JJM FHTCs
  • Water quality monitoring funds: only 0.38% spent, 1.62% diverted for construction
  • Only 11-19% of prescribed water quality tests conducted at Jal Nigam WTP labs
Source bodyComptroller & Auditor General of India (CAG) — audit reports
Reference numberReport No. 4 of 2026
Statusclosed (section: audit_report)
Year2026
Closing date
Documents1

Highlights & Points worth asking

Auto-generated, neutral observations. Auto-generated from public documents. May contain errors. Not legal or financial advice. Always verify against the linked original document. KaunZimmedar is a platform, not an authority.

No automated observations for this document. Read the documents below directly.

Documents

The original government PDF is the authoritative source — shown below, or open it full-screen in a new tab.

Audit_report 2026 125578-Report-No-4-of-2026-Report-of-the-Comptroller-and-Auditor-General-of-I.pdf
Tap “Open the PDF” above to view this document.

Discussion (0)

Citizens discussing these documents. A discussion space — nothing here is verified fact or an official finding. Reading is free; sign in to take part.

Open discussion (0) →